Year Cash Barrier Projects Client Approximate Project Area
2023
4-Laning of Boregaon Buzurg to Shahpur section of NH- 753L from km. 139.000 to km. 186.000 (length- 47km.) under Bharatmal Pariyojana in the state of Madhya Pradesh on Hybrid Annuity Mode.
Kalyan Toll Infrastructure Ltd.
25,000 MTR
2022
Construction of Reinforced Earth wall for Construction of 4-Lane Greenfield Delhi-Amritsar-Katra Expressway from junction with Jind- Panipat road (NH-352A) near Gangana village to junction with Jind-Karnal road (NH-709A) near Alewa village (Km. 60+800 to Km. 91+400) on Hybrid Annuity Mode under Bharatmala Pariyojana in the state of Haryana - Package - III.
KCC KATRA Expressway Pvt. Ltd.
10,000 MT
2022
Rectification of 01 No. black spot identified by Ministry of Road Transport & Highways (MORT&H) under jurisdiction of PIU-Chittorgarh at Km. 05+900 (JK Circle) on Rajasmand – Bhilwara section of NH-758 from Km. 0.000 to Km. 87.250 in the state of Rajasthan.
K. K. Gupta Constructions Pvt. Ltd.
2,000 MTR
2022
Construction of Four Lane Flyover with service road at the junction of NH-58E with NH-48 under annual plan 2021- 22 of road safety in the state of Rajasthan on EPC Mode for permanent rectification of black spot ID no. RJ-02/282
K. K. Gupta Constructions Pvt. Ltd.
1,500 MTR
2021
Construction of 8-Lane Expressway starting before KMP Expressway and ends at CH.- 47+000 near Khanpur Ghat (Km.- 18+500 to Km. 47+000) section of Delhi - Vadodara Green Field Alignment (NH-148N) on EPC mode under Bharatmala Pariyojana in the state of Haryana.
APCO Infratech Pvt. Ltd.
7,000 MTR
2021
Four laning work of Package-2 from km. 220.000 (near Kurankhand) to km. 270.000 (near Shelad) section of Amravati - Chikhli NH-6 in the state of Maharashtra to be executed as Hybrid Annuity Project under NHDP Phase - IV.
Rajpath Infracon NH-6 PKG-2 Pvt. Ltd.
15,000 MTR
2021
Four-Laning of Ausa - Chakur of NH-361 from km. 55.835 to km. 114.600 (Existing chainage: km. 470.000 to km 528.200) under NH (O) on Hybrid Annuity Mode in the state of Maharashtra.
Gangamai Industries and Construction Ltd.
9,000 MTR
2021
Balance Four-Laning work of Package-4 from km. 315.000 (near Nandura) to km. 360.000 (near Chikhali) section of Amravati - Chikhali NH-6 in the state of Maharashtra to be executed as Hybrid Annuity Project under NHDP Phase- IV.
Kalyan Toll Infrastructure Ltd
10,000 MTR
2021
Consultancy services for preparation of detailed design for construction of Ring Road for Rae-Bareli City (Phase- I) on Eastern side of NH-24B in the state of Uttar Pradesh.
Mahakaleshwar Infratech Pvt. Ltd.
12,000 MTR
2020
Development of Purvanchal Expressway (Package-III) from Jaraikala (Dist. Amethi) to Sidhi Ganeshpur (Dist. Sultanpur) (Km 79+900 to Km 121+600) in the state of Uttar Pradesh on EPC Basis.
APCO Infratech Pvt. Ltd.
7,000 MTR
2020
Casting and Erection of RCC Crash Barrier with Friction Slab at Aligarh to Kanpur Road project (Package -III)
APCO Infratech Pvt. Ltd.
9,000 MTR
2020
Casting and Erection of RE Wall from Tanot- Ramgarh- Bhadasar- Jaisalmer Section of NH-68, Rajasthan.
Brij Gopal Construction Co. Pvt Ltd.
10,000 MTR
2019
Casting and Erection of RE at Bhadrak-Baleshwar Section NH-16, in the state of Odisha.
Brij Gopal Construction Co. Pvt Ltd.
20,000 MTR
2019
Casting and Erection of RCC Crash Barrier with Friction Slab at Solapur-Bijapur Section NH-13, Maharashtra
IJM / SDPL
10,000 MTR
2019
Casting and Erection of RCC Crash Barrier with Friction Slab at Chikhali- Tarasod Section of NH-06, Maharashtra.
Welspun / APPL
15,000 MTR
2019
Casting and Erection of RCC Crash Barrier with Friction Slab at Jhansi-Khajuraho Pkg-II Section of NH-75/76, M.P.
PNC Infratech Ltd
14,383 MTR
2017
Casting and Erection of Crash Barrier at Nagpur – Mansar – Pauni, Section of NH-7, Maharashtra
Oriental Structural Engg. Pvt. Ltd.
12,000 MTR
Year RS Wall Projects Client Approximate Project Area
2024
Four Laning of Tarsod-Fagne (Package-IIB) section of NH6 from km.- 422.700 to km.- 510.000 in the state of Maharashtra to be executed on Hybrid Annuity Mode under NHDP Phase -IV.
Kalyan Toll Infrastructure Ltd. / AGROH Infrastructure Developers Pvt. Ltd.
68,000 SQM
2024
Construction of Vehicular Underpass with Service Road in Km.- 176+787 For Khed Railway Station, Gunde Phata in Km.- 191+900 and Construction of Vehicular Over Pass at 129+400 in Nadgaon village on National Highway No.- 66 in Raigad and Ratnagiri District in the state of Maharashtra.
Kalyan Toll Infrastructure Ltd..
35,000 SQM
2024
Balance work of Four Laning of Panvel-Indapur section of NH-66 (Old NH-17) from km.- 42.300 (KASU) to km.- 84.600 (Indapur) in the statae of Maharashtra under Bharatmala Pariyojana.
2023
Development of Six - Lane Access-Controlled Highway of DaatKali Tunnel - Dehradun of Ganeshpur - Dehradun Section of NH-72A from Km.- 16+380 to Km.- 19+785 (Design Chainage) in the state of Uttarakhand under Bharatmala Pariyojana on EPC Mode (Package-3).
KRC Infra Projects Pvt. Ltd.
18,000 SQM
2023
Construction of 4-Lane Banglore Chennai Expressway from km.- 180.000 to km.- 204.500 (Walajahpet to Arakkonam section in the state of Tamilnadu) under Bharatmala on Hybrid Annuity Mode (Phase III - Package II).
KCC WALAJAHPET Expressway Pvt. Ltd.
20,000 SQM
2023
Construction of Eight-Lane acces controlled Expressway from Km. 3.000 to Km. 20.200 (Shirsad to Akloli section - SPUR of Vadodara Mumbai Expressway) in the state of Maharashtra on Hybrid Annuity Mode under Bharatmala Pariyojana.
APCO Infratech Pvt. Ltd. / IRCON International Ltd.
12,000 SQM
2023
Six Laning of Varansi - Aurangabad section of NH-2 from Km. 786+000 to Km. 978+400 (Length - 192.400 Km) in the states of Uttar Pradesh & Bihar under NHDP Phase - V as BOT (Toll) on DBFO Pattern.
Welspun Enterprise Ltd. / Ayush Procon Pvt. Ltd.
10,000 SQM
2022
Rectification of 01 No. black spot identified by Ministry of Road Transport & Highways (MORT&H) under jurisdiction of PIU-Chittorgarh at Km. 05+900 (JK Circle) on Rajasmand – Bhilwara section of NH-758 from Km. 0.000 to Km. 87.250 in the state of Rajasthan..
K. K. Gupta Constructions Pvt. Ltd.
12,000 SQM
2022
Construction of Four Lane Flyover with service road at the junction of NH-58E with NH-48 under annual plan 2021- 22 of road safety in the state of Rajasthan on EPC Mode for permanent rectification of black spot ID no. RJ-02/282.
K. K. Gupta Constructions Pvt. Ltd.
12,000 SQM
2022
Construction of Reinforced Earth wall for Construction of 4-Lane Greenfield Delhi-Amritsar-Katra Expressway from junction with Jind-Panipat Road (NH-352A) near Gangana village to junction with Jind-Karnal Road (NH- 709A) near Alewa village (Km. 60+800 to Km. 91+400) on Hybrid Annuity Mode under Bharatmala Pariyojana in the state of Haryana - Package - III.
KCC KATRA Expressway Pvt. Ltd.
100,000 SQM
2022
Construction of 8-Lane Expressway starting before KMP Expressway and ends at CH.- 47+000 near Khanpur Ghat (Km.- 18+500 to Km. 47+000) section of Delhi - Vadodara Green Field Alignment (NH-148N) on EPC mode under Bharatmala Pariyojana in the state of Haryana..
APCO Infratech Pvt. Ltd.
40,000 SQM
2021
Four laning work of Package-2 from km. 220.000 (near Kurankhand) to km. 270.000 (near Shelad) section of Amravati - Chikhli NH-6 in the state of Maharashtra to be executed as Hybrid Annuity Project under NHDP Phase - IV.
Rajpath Infracon NH-6 PKG-2 Pvt. Ltd.
25,000 SQM
2021
Four-Laning of Ausa - Chakur of NH-361 from km. 55.835 to km. 114.600 (Existing chainage: km. 470.000 to km 528.200) under NH (O) on Hybrid Annuity Mode in the state of Maharashtra.
Gangamai Industries and Construction Ltd.
45,000 SQM
2021
Four-Laning of Katni Bypass section of National Highway- 30 (Old NH-7) from km. 359+375 to km. 378+555 having a length of 19.230 km in the state of Madhya Pradesh on EPC Mode.
Shreeji Infrastructure India Pvt. Ltd.PRL Projects & Infrastructures Pvt. Ltd.
25,000 SQM
2021
Remodeling of existing pucca ramps along right marginal embankment (RME) from R.D. 0m TO R.D. 10500m on city side to maintain accessibility from various villages to RME.
Irrigation & Flood Control Department (Delhi)
18,000 SQM
2021
Balance Four-Laning work of Package-4 from km. 315.000 (near Nandura) to km. 360.000 (near Chikhali) section of Amravati - Chikhali NH-6 in the state of Maharashtra to be executed as Hybrid Annuity Project under NHDP Phase- IV.
Kalyan Toll Infrastructure Ltd.
35,000 SQM
2021
Proposed Underpass/ Flyover at FNG, near Bahlolpur village, Noida, Uttar Pradesh.
New Okhla Industrial Development Authority
6,000 SQM
2021
Four-Laning of Chakur-Loha section of NH-361 from km. 114+600 to km. 187+800. (Existing chainage: km. 528+200 on MSH-3 to km 514+885 on MSH-2) under NH (O) on Hybrid Annuity Mode in the state of Maharashtra.
Kalyan Toll Infrastructure Ltd.
120,000 SQM
2021
Four Laning of Nanasa to Pidgaon from (Design CH:95+000/ Existing CH:95+000) to (Design 142+445/ Existing CH: 141+530) Section of NH-47 (Old NH - 59A) (Design Length-47.445 Km) under Bharatmala Pariyojana Phase-1 (Economic Corridor) in the state of Madhya Pradesh on HAM Mode- Package III (Indore-Harda).
Adani Road Transport Ltd
35,000 SQM
2021
Construction of Reinforced Earth wall for 4-Laning of Akola to Medshi from Km 0.000 to Km 47.700 (Design Chainage) of NH-161 including Bypasses at Patur and Medshi in the state of Maharashtra on EPC Mode.
Monte Carlo Limited
25,000 SQM
2021
Construction of ROB in Rehabilitation and upgradation of Allahabad bypass road junction, Allahabad city section of NH-96 from existing km. 135/230 to km. 153/000 (Design ch. 153.550 to 153.330) (excluding existing km. 148/600 to km. 149/900) to four Lane with paved shoulders in the state of Uttar Pradesh on (EPC) basis contract.
Prabha Engineering Ltd.
20,000 SQM
2020
Consultancy services for preparation of detailed design for construction of Ring Road for Rae-Bareli City (Phase- I) on Eastern side of NH-24B in the state of Uttar
Mahakaleshwar Infratech Pvt. Ltd.
35,000 SQM
2020
Construction of 4-Lane ROB at K.M. 30.00 on NH- 162-E (Pali-Nadol Road section) crossing the Falna – Marwar Railway section at L/C No. C-67 near Somesar in the state of Rajasthan.
MORT&H
12,000 SQM
2020
Balance Work of 4-Lane of Bareilly-Sitapur Section of NH- 24 from Km.-262 to km.-413.200 in the state of Uttar Pradesh.
Raj Corporation Ltd / Siddharath construction/ Jagdish saran (JV)
20,000 SQM
2020
Supply of RS Wall System for Bundelkhand Expressway (Package IV) Auraiya to Etawah, U.P.
Dilip Buildcon Ltd.
65,000 SQM
2020
Casting and Erection of RE Wall from Tanot- Ramgarh- Bhadasar- Jaisalmer Section of NH-68, Rajasthan.
Brij Gopal Construction Co. Pvt. Ltd.
45,000 SQM
2019
Casting and Erection of RE at Bhadrak-Baleshwar Section NH-16, in the state of Odisha.
Brij Gopal Construction Co. Pvt Ltd.
55,000 SQM
2019
Proposed ROB (2Lane) in Lieu of engineering L.C. No.- 175C at km.- 173/6-7 on Rewari – Jaipur section.
North Western Railway
11,000 SQM
2019
Casting and Erection of RE Wall at Mumbai- Vadodra Expressway, Vadodra, Gujarat.
Larsen & Tubro Ltd.
33,000 SQM
2019
Supply of RS Wall System for Sangli- Solapur Package IV: Mangalwedha to Solapur, NH-166, Maharashtra.
Dilip Buildcon Ltd.
1,10,000 SQM
2018
Casting and Erection of RE Wall at Chikhali- Tarasod Section of NH-6, Maharashtra.
Welspun / APPL
1,25,000 SQM
2018
Casting and Erection of RE Wall for the development of Purvanchal Expressway from Jaraikala (Amethi) to Sidhi Ganeshpur (Sultanpur), U.P.
APCO Infratech Pvt
40,000 SQM
2018
Casting and Erection of RE Wall at Chitradurga- Devangere Road Project, Karnataka.
PNC Infratech Ltd.
35,000 SQM
2017
Casting and Erection of RE Wall at Bhavnagar- Talaja, NH-8E, Gujarat
Sadbhav Engg Ltd.
40,000 SQM
2016
Casting and Erecton of RE Wall at Lambra- Shahkot Section of NH-71, Punjab.
Patel Infrastructure Pvt. Ltd.
48,000 SQM
2015
Casting and Erection of RE Wall at Delhi- Agra Section of NH-2, Haryana.
Larsen & Tubro Ltd.
1,15,000 SQM
2014
Casting and Erection of RE Wall at Rohtak- Hissar Section of NH-10, Haryana.
Sadbhav Engg Ltd.
67,000 SQM
2012
Casting and Erection of RE Wall at Indore-Devas section of NH3, M.P.
Gayatri Projects Ltd.
58,000 SQM